North Vancouver Townhome Renovation

In late August 2009 we began the renovation of a townhome in North Vancouver and decided to document each step of the way. As you scroll down the page you can see our 3 dimensional drawings, elevations and photographs as we progress through the design and renovation process. Each client of Cornerstone Kitchens & Design is able to see their newly designed kitchen before ever committing any money to the project.

Every week we have updated this page as the renovation moved forward. View the photographs and watch how we turn a design idea into a beautiful and functional work space.

While we don’t actually do the construction ourselves, as Project Managers we are involved in the overall process. We have some excellent contractors that we recommend to our clients who will meet with you and prepare a detailed quote.

R-Getting an update    R-Arlie Measuring 
Week 1    

R-1-Floorplan

R-1-Lv&DrmWall  R-1-Lv&DrmWall CAD 
 Old Kitchen Wall from Living Room New Kitchen Wall from Living Room
R-1-Kitchen   R-1-Kitchen CAD
Old Kitchen New Kitchen
R-1-Dining Rm wall  R-1-Dining Rm CAD 
Old Dining Room Wall New Dining Room Wall
R-1-Closet  R-1-Closet CAD 
Old Closet  New Closet
R-1-Sink Wall R-1-Sink Wall CAD
Old Sink Wall New Sink Wall

Week 2 & 3

R-2&3-Dining Rm wall   R-2&3-Dining Rm
 Dining & Living Room Wall Inside Kitchen
 R-2&3-Dining Rm wall2  R-2&3-Dining Rm2
Dining & Living Room Wall Removed  Dining & Living Room Corner Wall
R-2&3-Range wall   R-2&3-Range wall removed
 Range Wall  Range Wall Removed
 R-2&3-Closet Wall  R-2&3-Sink Wall
Closet Wall  Sink Wall

Week 4
The Cabinets are now ready for installation and our expert installer, Paul, is on site transforming the kitchen.

R-4-Arlie&Paul CAD  R-4-Paul 
Arlie & Paul working out some details  Paul Installing the Cabinets 
R-4-Paul&Arlie  R-4-Sink Wall 
Project Managing  Installation taking shape 
 R-4-Cabinet install R-4-Corner Cabinet install 
Install Day   
R-4-Job site   R-4-ExtCorner
Busy Job Site  Progress 
 R-4-ExtCounter  R-4-Base Cabinets
   

Week 5,6, & 7

When the cabinets have been installed, the Granite Company comes in to template for the countertops, this takes about 3 weeks from templating. We are now in the final stages of this Kitchen renovation, the wood floors have been installed and painting has been started. Final photographs are at the bottom of the page.

R-5,6,7-Range Wall  R-5,6,7-Range Wall2 
 Granite Installation  
 R-5,6,7-Sink Wall granite  R-5,6,7-Prep Sink
   
 R-5,6,7-Kitchen&Dining Wall  R-5,6,7-LvRm&Dining Wall
   

Week 8,9, & 10

Final stages of the renovation are now taking place. Appliances are being installed and painting is being finished. The family will be moving in within a few days.

R-8,9,10 DW Wall  R-8,9,10-Bar&Sink Wall 
 Tiling is being completed  
 R-8,9,10 Sink Wall  R-8,9,10-Fridge Wall
Appliances are in Almost there! 
CB Sink Wall CB Fridge Wall
Wow, the finished result Beautiful New Kitchen
CB Fridge Wall 2 CB Dining Room Wall
Range Wall  View from the Dining Room 
   
   

Thank you to our clients who allowed us to document this renovation and post it on our website.